Aerial view of Longview High School's softball complex, with green turf, covered structures, stands and surrounding parking, shown in the Oct. 19, 2026, bond update.

Longview ISD trustees approved a plan to help more Bailey Elementary students read, solve math problems and stay on track during their Oct. 19 meeting. Across the district, new classrooms, practice spaces and other bond projects continued to take shape.

The school improvement plan calls for more time on core skills, daily small-group help and close attention to each child's progress. Trustees approved it 7-0 with a group of routine items voted on together.

Trustees also heard how East Texas Montessori Prep Academy is strengthening early learning, reviewed construction across five major new facilities and received reports on school buses, campus health services, bilingual education and the responsible use of artificial intelligence.

Bailey's plan starts with each child

At Clarence W. Bailey Elementary, Principal Derrick Estes described a clear goal: help students master grade-level work by giving teachers the time, training and tools to meet each child's needs.

Bailey earned an overall score of 64, a D, in the state's 2026 school ratings. Its plan aims for a C or better in 2027, with a B as the higher goal.

The daily schedule protects at least 90 minutes for reading and 90 minutes for math. A separate 30-minute block gives students extra help or more advanced work. Teachers use short checks of student learning to see which skills need more practice, then work with small groups.

Estes stressed that the work reaches beyond a score on a chart.

"These are not percentages. These are names. These are faces," he told trustees.

Teachers also plan lessons together, practice how they will teach key skills and receive classroom coaching. Estes said teachers can adjust lessons and use other high-quality materials while keeping the same grade-level goals. Saturday classes provide another chance for students to strengthen their skills.

Getting students to school is part of the plan. Bailey's attendance rate rose from 93.7% to 95%, and the campus is working toward 96%. Staff call families about absences, connect students with mentors and help address barriers such as transportation. Estes said staff begin helping families before a child reaches the plan's 15-absence point for a home visit.

Building a strong start at Montessori Prep

East Texas Montessori Prep Academy's report focused on the habits and support that help young children learn.

Principal Faith Newhouse-Greer described Montessori training for teachers and campus leaders, stronger lesson planning, small-group teaching and regular coaching. Staff use reading and math checks, a Montessori lesson tracker and a campus dashboard to follow student progress.

Beginning-of-year reading assessments showed 42.7% of kindergarten students were on or above grade level. That gives teachers a starting point for daily lessons and extra help.

"Every child deserves a high-quality educational experience. Every teacher deserves the support needed to be successful, and every family deserves to feel connected to their child's school," Newhouse-Greer said.

Trustees asked about comparing kindergarten results for children who had attended district prekindergarten or Head Start. Campus leaders identified that as an area for further study.

Bond work brings more spaces into use

The Oct. 19 construction reports showed progress in spaces students already use and in buildings that will serve future classes.

E4, which oversees high school and athletic renovations, reported that two more sets of student restrooms at Longview High School were complete, including one in Lobo Coliseum. Work continued on other student and staff restrooms. The phased approach allows completed spaces to open while crews move to the next area.

Soccer upgrades and covered baseball bullpens were complete. New softball batting cages were in use, and the contractor's softball-complex work was substantially complete. A walk-through to identify remaining items was scheduled for Oct. 20.

At the high school's north parking lot, landscaping and permanent electrical service remained part of the final work.

The Little Theater was scheduled for improvements in December. Planning also continued for furniture, library work, doors and hardware. E4 said initial Lobo Stadium renovation proposals were expected in November. The team was working on a construction schedule that would preserve stadium use for graduation.

E4's construction report showed about $29.43 million below the original estimates for renovation work across Propositions A, C and D. That comparison excludes design and other fees. Some savings had already been used or moved to approved work, so the figure is not a final audited savings total or money all available for new projects.

Five major new buildings take shape

PROCEDEO manages the district's five major new-building projects. Its report showed continued work on the Career and Technical Education Center, multipurpose indoor facility, new swimming facility, Early Childhood Learning Center and Transportation Center.

At the career center, crews were working on interior walls, building systems and finishes. Rooftop air-conditioning units were in place.

The Career and Technical Education Center under construction, with exterior framing, equipment and fencing, in the Oct. 19, 2026, bond presentation.

Work continues at the Career and Technical Education Center in an image presented to trustees Oct. 19.

Structural framing for the multipurpose practice facility was about 70% complete. Framing had also begun in the adjoining portion. The 70% figure described the structural frame, not the whole project's completion.

Steel framing rises over the multipurpose indoor facility site, with concrete slabs and building materials in the foreground, in the Oct. 19, 2026, bond presentation.

Steel rises at the multipurpose indoor facility in the Oct. 19 construction update.

At the new swimming facility, crews were building masonry walls and preparing for structural wall materials expected in November.

Masonry walls, foundations, structural beams and equipment at the new swimming facility, shown in the Oct. 19, 2026, bond presentation.

Masonry and foundation work at the new swimming facility, shown in the Oct. 19 update.

All six building foundations at the Early Childhood Learning Center were in place, and framing had begun. The Transportation Center had received its permits, allowing crews to return to the site.

Concrete foundations and paving at the Early Childhood Learning Center site, with workers, equipment and a tree line, in the Oct. 19, 2026, bond presentation.

Foundations and site work at the Early Childhood Learning Center, shown in the Oct. 19 update.

The monthly change-order report included one materials-testing change that remained within the project budget.

Daily services help students stay ready to learn

The operations report followed the work that helps students get to school, eat well and receive care during the day.

The district's five-acre garden supplies fresh produce for student meals. School clinics recorded 6,468 visits from Aug. 17 through Oct. 6.

Nursing teams were strengthening health screenings and emergency training. That includes teaching staff CPR and how to use devices that can help restart a person's heart.

Transportation serves more than 4,100 students each day and travels more than half a million miles each year. Trustees asked for a year-to-year ridership comparison to help them assess future needs.

The district also reported $3,250 in donations. The East Texas Chapter of the Texas Restaurant Association gave $250 for culinary student activities. Credit Union of Texas gave $2,000 for State of the District, while Walker Quality Management Systems and Kilgore College each gave $500 for the event.

Language support and responsible use of AI

The annual bilingual education report identified 1,691 students in dual-language and English as a Second Language programs, about 21% of district enrollment.

Staff described support for teachers earning their state teaching credentials and lessons focused on students' language needs. An expanded partnership with Ensemble Learning supports middle and high school programs for students learning English.

Carl Mohn, director of AI strategy and applied learning, outlined a proposed first-year plan for artificial intelligence. It calls for reviewing tools already in use and training teachers to use them responsibly. The plan also sets out how tools would be approved and how concerns would be addressed.

He said staff must check AI-generated work and remain accountable for their choices. Tools used in decisions with major effects on students or staff would receive closer review.

"People remain responsible for every decision," Mohn said.

The presentation was an update on the proposed plan, not a board vote to adopt it.

Board actions and financial report

In addition to Bailey's improvement plan, the consent agenda included Budget Amendment No. 2, prior meeting minutes and the board's time-use tracker. Trustees approved the consent agenda 7-0.

Trustees also approved, by a 7-0 vote, the trained district administrators who will evaluate teachers during the 2026-27 school year.

A separate 7-0 vote approved an agreement with East Texas Baptist University that lets future teachers gain classroom experience in Longview ISD. District teachers will mentor the candidates, while university staff help supervise their training. The agreement does not allow the candidates to serve as substitute teachers.

Average daily attendance through Oct. 2 was 7,315, slightly above the 7,300 assumption used to build the 2026-27 budget. Average daily attendance measures how many students attend school each day; it is different from the total number enrolled. Finance staff did not recommend changing the year's revenue forecast at that point and planned to keep checking attendance and state funding every six weeks.

The August year-end financial report was still being checked. The books had not been fully balanced or audited. The report showed an operating shortfall of about $2.08 million before remaining entries and adjustments. Staff cited pending changes involving softball expenses, property-sale proceeds, state revenue, salaries and tax collections. Staff expected the year to end near balance or with money added to reserves. The figures were still awaiting a final audit.

View the Oct. 19 meeting agenda and presentations.