Workers renovate the Longview High School cafeteria in a photograph presented to the Bond Oversight Committee Aug. 4.

Longview High School's expanded cafeteria was expected to be ready for students when classes begin Aug. 17, project leaders told the Longview ISD Bond Oversight Committee during its Aug. 4 meeting.

The committee reviewed summer renovations, parking improvements and progress on five new facilities. Members also asked about school meals, construction schedules and pedestrian access across Hawkins Parkway.

Preparing for students

John Erickson of E4 reported that crews had spent the summer renovating about 75,000 square feet of high school space, including classrooms, hallways and the cafeteria. Classroom and hallway work was nearing completion, with furniture being moved back and final repairs and touch-ups remaining.

Work continued on cafeteria flooring, paint and other finishes. Erickson said the space was expected to be operational for the first day of school after required inspections. A ribbon-cutting was planned for Aug. 14 following staff convocation.

The cafeteria expansion adds more than 4,300 square feet of indoor dining space. Samuel Kington, chief of facilities and operations, said two additional serving lines, new seating and a revised layout were intended to help students move through the cafeteria more efficiently.

Members asked about menu choices and food availability for students eating later. Kington said he would seek additional information from Child Nutrition and described student surveys being used to guide menu planning.

Restroom work was being completed in phases. Most of the restrooms then under renovation were expected to open for the first day of school, with remaining areas scheduled for work in small groups to limit disruption to classes.

Erickson also reported that the north parking lot expansion was expected to add about 326 spaces before the first home football game. That project is separate from the shared parking area being built for the softball complex and new swimming facility.

New buildings and construction schedules

Paul Miller of PROCEDEO reported that plumbing, air-conditioning and fire-sprinkler work was advancing inside the new Career and Technical Education facility.

At the multipurpose indoor facility, production of prefabricated wall panels was about three weeks behind schedule. Miller said installation was expected to begin Aug. 17 and that the construction method would allow crews to recover time once panels arrived.

Work on the new swimming facility included the competition and warm-up pools, access drives and shared parking. Crews were working to make some of that parking available for football traffic, but Miller said the paving still required additional time.

The Early Childhood Learning Center's contractor had requested a 101-day extension after additional stormwater drainage design and permitting work. The request proposed moving substantial completion from November 2027 to February 2028. District officials were still negotiating the request; the extension had not been approved.

Matthew Prosser, chief of strategic initiatives, said the programs intended for the new center would continue at Playing for Keeps during construction.

Kington reported that trustees had approved an approximately $7.4 million guaranteed maximum price for Jackson Construction's Transportation Center work. The price was about $230,000 below the construction budget and included a $500,000 contingency for unexpected costs.

Miller said construction was expected to begin in August once the required permits were obtained.

Planning for access

Committee members also asked about a pedestrian bridge across Hawkins Parkway. Erickson said the district and city were discussing the design and accessibility requirements. The bridge's final design had not been settled.

Design work continued on Lobo Stadium and related improvements, with planning for athletic facilities north of Hawkins Parkway to follow.

The committee's next meeting was planned for Nov. 2 in the renovated Longview High School cafeteria.