Longview ISD's Bond Oversight Committee met in the renovated Longview High School cafeteria Nov. 2 to review completed summer work and plans for the next stage of campus construction.
Project leaders reported that the cafeteria, north parking lot and softball field were serving students and visitors. Members also asked about pedestrian lighting, parking and the order in which new buildings and renovations would be completed.
Improvements in use
The cafeteria was ready for breakfast on the first day of school, said Samuel Kington, chief of facilities and operations.
John Erickson of E4 said first-floor classrooms had been renovated, with restroom work continuing. Crews planned to complete second-floor classrooms and other academic spaces the following summer before finishing remaining administrative areas.
The north parking lot was in use for football games and other activities, with landscaping and final repairs still underway. Softball players had begun practicing at the new complex. Custom lockers were being manufactured, and crews were addressing finishing work.
Erickson said a proposed furniture purchase would replace student and teacher desks and chairs that needed updating. Installation was planned for spring break if trustees approved the purchase.
Stadium work and pedestrian access
Erickson said the first phase of Lobo Stadium work could begin after football season if trustees approved its construction price. Work from the top of the bleachers to the field was planned to finish before the next football season.
Separate work behind the visitors' stands would continue longer, with the construction area fenced off. The design team was refining plans for visitors' locker rooms, concessions and related facilities.
Committee members asked about recognizing championship teams as graphics were replaced. Erickson said graphics plans were being discussed, with some work to follow later construction phases.
Members also raised questions about lighting for people crossing Airline Drive during evening events. Erickson said the district was working on improvements to the existing crossing and would look at adding lights.
New facilities take shape
Paul Miller of PROCEDEO reported that the Career and Technical Education facility was about halfway complete. Painting and tile installation were underway in some areas while crews continued plumbing, electrical and air-conditioning work elsewhere. He gave a tentative completion target between July and September 2027.
Structural steel was rising at the multipurpose indoor facility. Miller said about three-fourths of the field house steel was in place, with steel work on the adjoining office and other spaces less advanced.
At the new swimming facility, the competition and warm-up pools were in place, and construction was moving above ground. Miller projected completion of the multipurpose and swimming facilities between October and December 2027.
Members asked how that schedule would affect renovations at the existing swimming facility. Erickson said work involving that space and the tennis courts would wait until the new swimming facility was ready.
At the Early Childhood Learning Center, Miller reported that steel and framing work was underway in three of six building sections.
The Transportation Center had completed plan review. Miller said crews were waiting for the site to dry before proceeding with preparation for the building foundation. The completion target was between July and September 2027. Kington said a move at the start of school would be a tight schedule and might occur after the first week or two of classes.
Committee business
Wayne Guidry reviewed the district's bond financing assumptions and debt repayment.
The committee approved the Aug. 4 meeting minutes without opposition.
Matthew Prosser, chief of strategic initiatives, invited members to suggest bylaw changes before a planned December review by trustees. Any changes would require Board approval.
Prosser announced Feb. 1, 2027, as the next meeting date. The Nov. 2 meeting concluded about 7 p.m.