Longview High School's cafeteria, classrooms and restrooms were the focus of a summer construction update to the Longview ISD Bond Oversight Committee on May 4.
Project leaders outlined work scheduled to begin as soon as students leave for summer break. Members also asked how the district would maintain renovated spaces, meet students' daily needs and plan the next round of athletic facility upgrades.
A busy summer at the high school
John Erickson of E4 said crews would begin the next phase of high school renovations the Saturday after the last day of school. The work includes first-floor classrooms and common areas, spaces around Lobo Coliseum, and the cafeteria expansion.
The cafeteria project was planned for a 10-week construction window. Samuel Kington, chief of facilities and operations, said the cafeteria would be ready to serve students on the first day of school.
Restroom renovations would continue in phases. Erickson said crews would finish as many as possible over the summer, then close selected restrooms for work after classes resume.
At the softball complex, Erickson reported that the playing field was complete and construction continued on support buildings and batting cages. He expected the buildings to be largely finished in mid- to late July.
Lobo Coliseum was scheduled for interior painting and seating improvements over the summer. Erickson said a new scoreboard package had been purchased and electrical work was underway to prepare for installation.
Questions about daily use
Committee members asked about cleaning, drinking fountains and ways students could heat food in the cafeteria.
Kington said the cafeteria furniture plan included space for several microwaves. He also agreed to check concerns about water-bottle filling stations.
New floors that do not require waxing were intended to make cleaning easier, Kington said. He described monthly campus surveys used to review custodial service and make adjustments.
Members also asked how future renovations would fit with new construction. Erickson said architects were coordinating exterior materials and colors so the high school's older buildings and new facilities would look more unified.
Plans for tennis courts and other facilities north of Hawkins Parkway were still being developed. Erickson said work involving the existing swimming facility would wait until the new pool was ready. Final layouts would depend on surveys, available space and the order in which projects could be completed.
New facilities take shape
Paul Miller of PROCEDEO reported that foundation work and steel construction were moving forward at the new career and technical education facility. Three of its five foundation phases were complete, with crews working on the remaining two.
At the multipurpose indoor facility, crews were finishing foundations and preparing an emergency access lane needed before steel construction could begin.
Excavation and grading continued at the new swimming facility as crews prepared the competition and warm-up pools for concrete.
For the Early Childhood Learning Center, Miller said revised drainage plans, including a detention pond, were awaiting city approval. He said the contractor hoped to begin foundation work that week.
The Transportation Center remained in design. Miller said completed drawings were expected in June, followed by city review and permits before construction.
Miller also reported that high school contractors had extended workdays and added weekend work to make up time lost to rain.
The committee approved the minutes of its February meeting without opposition. The May 4 meeting ended at 6:56 p.m.