Construction continues at the Longview High School softball complex in a Jan. 5 photograph presented to the Bond Oversight Committee Feb. 2.

Longview ISD's planned Transportation Center was being redesigned as a single building to meet staff needs within its construction budget, project leaders told the district's Bond Oversight Committee on Feb. 2.

The committee met in the Longview High School library to review construction progress and plans for summer renovations. Members asked about parking, pedestrian access, future fine arts improvements and how the district would set priorities for remaining work.

A new plan for transportation

Paul Miller of PROCEDEO said an earlier two-building design could not be brought within the construction budget. The project team was working with transportation staff and a new architect on a single-building plan.

Samuel Kington, chief of facilities and operations, said the first design included more space than staff had requested. The revised plan was smaller but still provided the space the department needed.

Miller said the architect had completed an initial set of drawings. Final drawings, city permits and approval of the construction price were still needed before crews could begin building.

Preparing for summer work

John Erickson of E4 outlined plans to expand and renovate the high school cafeteria during a nine-week summer construction window.

The design would enclose the covered breezeway to add dining space while preserving access between buildings. Erickson said the goal was to have the cafeteria ready to serve students when classes resume.

Matthew Prosser, chief of strategic initiatives, said Child Nutrition was planning to continue serving students attending summer camps and other activities while the cafeteria was under construction.

Summer renovations also would cover first-floor classrooms and hallways in the main building and academic areas near Lobo Coliseum.

Restroom work would be phased. Erickson said crews would complete as much as possible during the summer, then close and renovate selected restrooms after school begins.

He reported that second-floor hallway improvements were largely complete. Other painting and wall work had been done at night and during the holiday break.

Construction and access

At the new career and technical education facility, Miller reported that most underground utilities were in place and foundation work was underway. Crews at the multipurpose indoor facility were preparing the site for utilities and foundations.

The new swimming facility still needed city permits and Board approval of its construction price before work could begin, Miller said. City permits also were pending for the Early Childhood Learning Center.

Erickson said material deliveries and utility connections were affecting the softball complex's schedule. He said staff had a plan for an alternate playing location while crews worked toward opening the new field.

The north parking lot expansion was nearing the bidding stage. Erickson said the goal was to have it available for graduation, although landscaping might continue afterward.

Members asked about walking routes between the parking areas and the main campus. Erickson said sidewalk plans and the accessibility requirements for a possible pedestrian bridge were still being worked out.

Planning the next improvements

Committee members also asked about the band hall, fine arts spaces and Mickey Melton Performing Arts Center.

Erickson said some renovations would have to wait until new buildings opened and classes could move, freeing space for construction. Detailed plans for the band area were still in an early stage.

District leaders said remaining work would be prioritized by need and kept within the purposes voters approved.

The committee approved the October 2025 meeting minutes without opposition. Prosser proposed May 4 for the next quarterly meeting.