Summer renovations at Longview High School and the schedules for new bond-funded buildings drew questions from Longview ISD's Bond Oversight Committee on May 5.
Project leaders outlined work planned for classrooms, restrooms, the cafeteria and athletic facilities. Members asked how the district would coordinate construction, gather student input and keep the community informed as plans changed.
Preparing for summer renovations
John Erickson of E4 said work on the high school's second floor would begin during the summer. The renovations included flooring, paint, lighting, ceilings and wall finishes, with additional work to follow in later phases.
Roof replacements for the main high school building, ninth-grade wing and Lobo Coliseum also were planned to begin during the summer.
Erickson said an architect had been selected for renovations that included the cafeteria and restrooms, but the architect's contract and detailed designs still had to be completed. Restrooms would be renovated in sections so other facilities could remain available to students.
Samuel Kington, chief of facilities and operations, said the architect was expected to meet with students before the end of the school year to hear their ideas. Erickson said he had already heard from students about their needs and concerns.
The cafeteria's final design and construction schedule had not been settled. Erickson said the amount of expansion and the structural work required would help determine what could be done while school was in session.
Reviewing project schedules
Paul Miller of PROCEDEO reported that designs for the career and technical education center and multipurpose indoor facility were about halfway complete. The swimming facility was at an earlier design stage.
He presented plans to begin construction on those three facilities late in 2025, with completion targeted for April through June 2027.
Committee members questioned why projected completion dates had moved beyond earlier expectations and asked for clearer information they could share with the community.
Miller said changes to the multipurpose facility's location and the related relocation of the softball field had affected planning. District representatives said they were working with architects and construction managers to coordinate tasks and shorten the process without reducing quality.
Members also asked how the district would balance priorities among the new buildings and renovations. Matthew Prosser, chief of strategic initiatives, said the district could advance several projects at the same time.
Considering how facilities will be used
The swimming facility prompted questions about pool dimensions, the roof, air quality and input from people who use competitive swimming facilities.
Miller said the design was still being developed and that the swim coach had participated in design meetings. No final pool dimensions or roof design were approved at the committee meeting.
Erickson also reported that new lighting was operating at the baseball field and Judson stadium. Lobo Stadium's new lights were installed, with final programming still to come. Coliseum lighting work was planned after graduation.
Members asked about stadium handrails, soccer facilities, the band hall and other improvements. Project leaders described work still being evaluated or sequenced around higher-priority renovations and new construction.
The committee approved the minutes of its Feb. 3 meeting and discussed possible adjustments to future quarterly meeting dates.
View the May 5 meeting agenda.